Network Upgrade – Sunshine Avenue
19 November 2024
At Sunshine Avenue, JE are upgrading the mains cables prior to upgrading supplies to necessary properties.
- Phase 1 – Working northbound on Sunshine Avenue
from 14 October 2024 until 6 November. - Phase 2 – Working southbound on Sunshine Avenue
from 7 November until 6 December.
JE will be in touch with customers whose properties require an enhanced supply. These works will take place in January 2025.
Please visit www.jec.co.uk/roadworks for updates.