GOJ Drainage Maintenance
24 May 2023
June – September 2023
From the beginning of June 2023 to the beginning of September 2023, Drain it Ltd on behalf of the Government of Jersey are carrying out foul sewer rehabilitation on a number of roads within the Parish of St Saviour.
The works will be carried out both during the day and night, the road affected will be closed for the duration of the works.
Below is the schedule for the works and the various roads it will affect.
All occupiers of property will be notified on how they may be affected.
Start Date | End Date | Day works (8am – 8pm) Night works (8pm – 8am) | Road affected |
---|---|---|---|
05.06.2023 | 09.06.2023 | Day | Les Routeurs |
12.06.2023 | 12.06.2023 | Day | Rue du Pont |
13.06.2023 | 20.06.2023 | Day | Rue de la Guilleaumerie |
23.06.2023 | 24.06.2023 | Day | Rue de la Guilleaumerie |
26.06.2023 | 28.06.2023 | Day | Rue du Chateau Clairval |
29.06.2023 | 03.07.2023 | Day | Rue de St Mannelier |
04.07.2023 | 06.07.2023 | Day | Mont Sohier |
10.07.2023 | 11.07.2023 | Night | Mont Sohier |
12.07.2023 | 21.07.2023 | Night | Rue a la Dame |
24.07.2023 | 27.07.2023 | Night | Grands Vaux |
27.07.2023 | 27.07.2023 | Night | Rue a la Dame |
31.07.2023 | 02.08.2023 | Day | Fosse a L’Ecrivain |
For further information, please contact Drain It LTD on 720988 or email: [email protected]