June – September 2023

From the beginning of June 2023 to the beginning of September 2023, Drain it Ltd on behalf of the Government of Jersey are carrying out foul sewer rehabilitation on a number of roads within the Parish of St Saviour.

The works will be carried out both during the day and night, the road affected will be closed for the duration of the works.

Below is the schedule for the works and the various roads it will affect.

All occupiers of property will be notified on how they may be affected.

Start DateEnd DateDay works (8am – 8pm)
Night works (8pm – 8am)
Road affected
05.06.202309.06.2023DayLes Routeurs
12.06.202312.06.2023DayRue du Pont
13.06.202320.06.2023DayRue de la Guilleaumerie
23.06.202324.06.2023DayRue de la Guilleaumerie
26.06.202328.06.2023DayRue du Chateau Clairval
29.06.202303.07.2023DayRue de St Mannelier
04.07.202306.07.2023DayMont Sohier
10.07.202311.07.2023NightMont Sohier
12.07.202321.07.2023NightRue a la Dame
24.07.202327.07.2023NightGrands Vaux
27.07.202327.07.2023NightRue a la Dame
31.07.202302.08.2023DayFosse a L’Ecrivain

For further information, please contact Drain It LTD on 720988 or email: [email protected]